The
New Year brings with it Resolutions
and ours on the Project is to
maintain a flow of information
because reorganisations in the
Project should allow us to move
forward and so to have items
of information and progress
that we can communicate on a
regular basis.
As
of 31 December 2006 the Project
has undergone four main areas
of reorganisation and a Press
Release was issued as follows:
The
Board of Muscat Golf Course
Project LLC is pleased to
announce the support of Oman
Arab Bank and Bank Dhofar,
jointly providing the financing
requirements necessary to
ensure the successful completion
of the residential phase of
the project. The Board would
also like to take this opportunity
to thank Government of Oman
and their Ministries for the
ongoing support and assistance
provided by them. Without
this support the project could
not have progressed to the
stage where it can now move
forward.
The
Board has also confirmed the
transition to Phase 2 of the
project. With Laing Oman having
successfully brought the project
through Phase1, Cowi and Partners
LLC, in an extended role,
will now lead the professional
consultancy and project management
team which includes Majan
Engineering Consultancy and
Dave Thomas Golf Design. The
overall Master Plan and concept
architects are the world-renowned
Wimberley, Allison, Tong and
Goo.
With
all villas now sold and only
a small number of apartments
remaining for sale, the construction
of the residences is scheduled
to commence from the first
quarter of 2007. It is intended
to appoint a contractor of
international standing to
deliver this important part
of the project on a turnkey
basis.
It
is confirmed that the golf
course will "go green" in
the coming year, with Muscat
Golf & Country Club on schedule
to be the home of the Sultanate's
first grass golf course.
The
Board of Muscat Golf Course
Project has also announced
two important appointments
of new Members joining the
Board : Mr. PY Venkataraman,
the Deputy General Manager-
Credit for Oman Arab Bank,
as the senior representative
of the banks and Mr. Nick
Pattison, formerly Chairman
of Shell Oman Marketing.
HH
Sayyid Rawy bin Kais confirmed
that " With the gracious support
already given by the government,
the recently concluded support
of the banks and a renewed
focus for the project team,
the Board fully anticipates
the project will fulfil the
expectations of the promoter
HH Sayyid Kais Bin Tarik and
of the numerous home owners
who have placed their faith
in the Muscat Golf Course
Project."
Scanned
excerpts from 7th January 2007
morning's English speaking Oman
daily newspapers are attached.
For
those who are not aware COWI
is an independent Danish firm
of Consulting Engineers and
planners, founded in 1930 and
has had a permanent office in
Oman since 1986 where it trades
in the name of Cowi and Partners
LLC.
COWI
maintains absolute independence
from contractor's, suppliers
and manufacturers and is firmly
established in Oman as an international
consultant having earned a reputation
for excellence in the fields
of architectural, civil and
structural works. Furthermore
COWI's services are used by
various government ministries
as specialist advisers for complex
projects throughout the Sultanate.
Recent
projects that COWI has been
involved in include the Guest
Palaces at Bait Al Baraka and
Qasr Al Alam, the Grand Mosque,
the Chedi hotel Muscat, the
University of Nizwa and the
new Muscat Concert Theatre.
Currently COWI are JV consultants
for the expansion works of Seeb
and Salalah International airports.
COWI
bring a wealth of local knowledge
and experience to this second
phase of the Project which comprises
the construction of the residential
units, roadways and infrastructure.
Cowi's strengths in supervision
of construction, testing and
commissioning together with
their procurement services well
experienced in the local market
will lead on naturally from
the solid base provided during
the Laing phase of the project.
This
reorganisation also has the
advantage of simplifying the
decision making process and
speeding up approvals without
compromising the levels of quality
that we are committed to providing
all Buyers.
COWI
are now finalising negotiations
with Contractors preparatory
to recommending to the Board
Contract Award and announcements
will be made public in this
area within the next four weeks.
We
are confident that with the
support of the banks now in
place 2007 will bring with it
the activity and progress that
we all have been waiting for
to enable the Project to move
to a successful conclusion.
|